AMENDMENT HISTORY
 
CP1.B     Security Lodgement Form 1 Oct 2007 Original
           
      3 Feb 2015 Annexure B (Security Lodgement Form) amended to include bond multiplier
4 Jan 2017 IRC Requirements added
   
CP1.C   Standard Subdivision Inspection & Test Plan 1 Oct 2007 Original
      3 Feb 2015 Annexure C (Inspection and Test Plan) has been amended to:
- Reflect CCTV stormwater testing (if required) [Refer Page 4]
- Reflect that CCTV testing may be required at off defects liability [Refer Page 7]
   
CP1   Construction Procedures 2 Apr 2013

Table CP1.15.1 Use of CCTV. CHRC - Yes.  All other Councils - No

Deleted table CP1.27.1 relating to non 100% completion of electrical reticulation

           
      3 Feb 2015 Page CP1-10 Line inserted for CCTV inspection of Stormwater lines (where required) - this is in turn qualified by Table CP1.27.1 later in the document.

Table CP1.23.1 As constructed submission requirements has been added.

Table CP1.27.1 CCTV Inspection On and Off Maintenance has been amended.

Table CP1.28.1 Incomplete Works Bond Multiplier has been added.
      4 Jan 2017 IRC requirements added
   
AP1   Approval Procedures 1 Oct 2007 Original
           
      3 Jan 2017 IRC requirements added
           
      4 April 2019 Clarification of drainage design (quantity and quality) expectations in clauses AP1.04.01 and drainage easements in AP1.04.04

Clarification of timing for provision of Ergon and Telecommunications information in AP1.09.02

Design submission AP1.11 updated to include Statement of Compliance and IDAS Forms

Other minor changes to correct or update terminology and reference documentation
AP1.A   Statement of Compliance, Engineering Design 1  Oct 2007 Original
      2 Feb 2017 LSC and GRC requirements added
           
      3 August 2019 Sewer Reticulation added to table of compliance
   
C202   Rural Road Clear Zones 1  Nov 2013 New Document
   
C245   Asphalt Concrete Surfacing 1 Jun 2013 Amendments to asphalt thickness & compaction requirements.
           
   
C263   Guide Posts 1 Oct 2007 New Document; No amendements
   
C264   Guard Fencing 1  Oct 2007 New Document; No amendements
   
C273   Landscaping 1  Oct 2007 Original
   
C273   Landscaping 3  Jan 2017 IRC requirements added. References to Lorsban removed.
   
C401   Water Reticulation   Feb 2015 Removed - Refer to Design Specification D11 for Construction Information
   
C402   Sewer Reticulation   Feb 2015 Removed - Refer to Design Specification D12 for Construction Information
   
C501   Bushfire Protection 2 Jan 2017 IRC requirements added plus a new requirement for turning areas within fire breaks
   
C273   Landscaping 2 Feb 2015 LSC and GRC requirements added, including plant lists.
   
C501   Bushfire Protection 1 Oct 2007 Original
   
D1   Road Design 2 March 2012 Various references amended

Vehicle access requirements for private driveways and battleaxe lots for post amalgamation Councils have been adopted to supersede former Council requirements

Geometric urban road design requirements for post amalgamation Councils have been adopted to supersede former Council requirements(For additional information see Summary of Post Amalgamation Changes)

Additional concrete footpaths are now required by Central Highlands Regional Council.
 (For additional information see Summary of Post Amalgamation Changes)


The traffic threshold for access streets and minor collectors has been reduced for former PDSC local government area. 
(For additional information see Summary of Post Amalgamation Changes)

All 4 Councils have adopted altered requirements for rural roads. Banana Shire Council have altered the traffic thresholds for various rural road configurations. ARI design requirements have been included by some Councils
      9 July 2018 Removal of driveway sections
           
      3  Nov 2013 New section for rural road clear zones
           
      4 Dec 2013 Maranoa changes to:

Rural roads Table D1.21.03 pathway requirements on collector roads (Tables D1.06.04 to D1.06.06)

New commercial category; Table D1.06.13
           
      5  May 2014 All references to BSC footpath widths changed to 2.0 metres.
           
      6 Jan 2015 LSC and GRC requirements added.
           
      7 Jan 2018 IRC requirements added
           
      8 Mar 2018 GRC requirements added
           
      9 Jul 2018 Removal of driveway sections
   
D2   Pavement Design 2 Mar 2012 Spray seals no longer accepted for urban residential streets for any Council. (For additional information see Summary of Post Amalgamation Changes)

Minimum thickness requirements for asphalt pavement DG14 to sub arterial, industrial access and industrial collector have been increased

Design of spray seal removed and replaced with reference to Austroads Design of Sprayed seals 1990
           
3 Sep 2014 Asphalt thickness amended in D2 Pavement Design Specification
      4 Feb 2020 Table D02.13.02 Preferred Asphaltic Concrete Applications amended for the DG10 depths of Access Place & Street and Park Residential to 25mm, and DG14 depths for Access Place & Street, Minor & Major Urban Collectors, Trunk Collector Street, Sub Arterial and Park Residential to 40mm.
   
D3   Structures and Bridges 2  Mar 2012 Austroads reference amended
   
D4   Subsurface Drainage 2 Mar 2012 Use of strip drain as well as slotted pipe permitted
   
D5   Stormwater Design 2 Mar 2012 Interallotment drainage design class requirements have now been agreed by all Councils as follows:  Generally Level 2 will apply.  Level 3 inter-allotment drainage may be required by the Local Government in some instances (eg. steep slopes) (For additional information see Summary of Post Amalgamation Changes)

All Councils are now in agreement regarding ARI design criteria. (For additional information see Summary of Post Amalgamation Changes)

IFD charts adopted for different parts of local government areas.

IFD Curves are now greatly simplified for RRC. References to QUDM updated.

Reference to approved pipe material included (RCP and FRC).
           
      3 Apr 2015 LSC and GRC requirements added.

Inter-allotment drainage requirements clarified.
           
      4 Jan 2017 IRC requirements added
           
      5 April 2019 D5 Amendments
           
      6 Aug 2019  
           
      7 Sep 2020 Update to Lawful Point of Discharge. Bio-Retention Systems and Vegetated Stormwater Assets have been moved from D7.
      8 Mar 2022 1. Table D05.04.1 amended to clarify its use for minor system design only. Design AEPs/ ARIs are unchanged.
2. New Table D05.04.2 provided to clarify major system AEPs/ ARIs design requirements.
   
D9   Cycleway and Pathway Design 2 Mar 2012 Austroads reference amended
Minimum pathway width amended from 1.0 m to 1.2m, and for dual use pathways from 2.0m to 2.5m in Table D9.05.01
Horizontal clearances amended in Table D9.05.01
   
D11   Water Reticulation 2 Apr 2013 New combined Design and Construction Specifications in draft for comment until 21st June 2013
           
      D Dec 2014 LSC and GRC requirements added and multiple additional changes.
           
      E May 2015 Changes to clarify LSC requirements. Note 2 new tables of difference11.08.02 (Use of DI pipe) and 11.08.05 (Flanged valves and tees) were necessary to do this.
           
      F Dec 2016 Changes initiated by RRC details at this link.
           
      G Jan 2018 IRC added
           
      I Oct 2018 D11 Changes
           
      J Dec 2018 MRC kerb painting for hydrants updated
           
      K April 2019 Clause for fire hydrants and urban spacing amended:

D11.11.02 For urban areas, fire hydrants shall be at maximum 80m spacing for all non-trunk water supply network mains and no more than 20m from the last furthest property frontage in a cul-de-sac. and located so that they comply with AS2419 hydrant location

           
      J Feb 2020 Table D11.09.01 PVC Minimum Water Main Pipe Classes amended Gladstone Regional Council from PN16 to PN12.5 for the PE pipe class.
      L Jan 2022
  1. Table D11.06.01 LSC network analysis software amended to INFOWORKS

  2. D11.06.04 reworded for clarity (this clause relates to hydraulic capacity)

  3. D11.06.05 reworded to amend approach to areas of allotments which cannot be serviced by water supply

  4. Table D11.07.01 Design Demands amended for LSC and GRC

  5. D11.07.03 and Table D11.07.02 amended to clarify water network modelling design requirements in relation to minimum pressures and node levels.

  6. D11.11.04 amended to clarify that GRC customers supplied via a constant flow network are not provided with a fire service

   
D12   Sewerage Reticulation 1 Feb 2013 New combined Design and Construction Specifications in draft for comment until 21st June 2013
           
      D Dec 2014 LSC and GRC requirements added and multiple additional changes.
           
      E May 2015 Clarification of LSC requirements for various items including use of vertical/horizontal curves and testing.
           
      F July 2016 Amendment of RRC requirements for Sewerage easements
           
      G Dec 2016 Changes initiated by RRC details at this link.
           
      H Jan 2018 IRC added
           
      K Oct 2018 D12 Changes
D15   Geometric Road Design   Jun 2018 New document
   
PS-4   Polyethelene Pressure Pipe B Jan 2018 -
      C May 2022 Pressure classifications updated to PN16
           
PS-28   Gaskets C Sep 2022 -
           
 

Disclaimer Date Last Modified 21/04/2022 - Website best viewed at 1024 x 768 pixels CMDG Home Page Visitor Hit Counter